We found out today that it was ok to use 100mm blocks laid flat as a substitute for a 215mm specified block. This will help with the manual handling issue we would have had if the 215mm block were to be used. The plasterers are back today and will be plastering in the intello membrane along with the completion of the 1st fix electrics. The intello grommets work great for a single cable we have yet to use the muliti cable grommets.
Air-tight grommets for cables
Plastering into the air-tight mesh / tape
New slab poured for rear extension