Tuesday, 9 November 2010

Site Manager Ian Davenport's Site Progress Diary

1st fix joinery and sheeps wool insulation. Sheeps wool is difficult to cut with a Stanley knife, it is cut more successfully with a large pair of scissors. Pour rear conc floor slab.
Two layers of timber battening on external wall 

Sheepswool insulation friction fitted between battens

Full-fill sheepswool insulation between battens
Reinforcement & DPM under slab with drainage penetration

New slab to kitchen being poured & leveled