Thursday 24 February 2011

Site Manager Ian Davenport's Site Progress Diary

During the past week, we have completed the decoration, commissioned the boiler and solar panels, commissioned the MVHR and are completing the external works.

David (Sanctuary's Clerk of Works) and I have just returned from St Lukes and the MVHR is running and the rads are off, the temp in the bedrooms is almost too warm! The ext temp is 13deg and the attached photo shows the solar panels heating to 59deg.

Solar Thermal Info Panel on Rotex Unit
Decorations Complete
MVHR wall mounted outlet to front bedroom
Insulation in Loft & Insulated MVHR intake