Thursday 24 February 2011

Site Manager Ian Davenport's Site Progress Diary

During the past week, we have completed the decoration, commissioned the boiler and solar panels, commissioned the MVHR and are completing the external works.

David (Sanctuary's Clerk of Works) and I have just returned from St Lukes and the MVHR is running and the rads are off, the temp in the bedrooms is almost too warm! The ext temp is 13deg and the attached photo shows the solar panels heating to 59deg.

Solar Thermal Info Panel on Rotex Unit
Decorations Complete
MVHR wall mounted outlet to front bedroom
Insulation in Loft & Insulated MVHR intake

Friday 18 February 2011

Site Manager Ian Davenport's Site Progress Diary

Over the last 4 days we've been decorating , testing the MVHR and completing the glazed tiling.
Radiators moved closer to wall for more space

Small 'back-up' radiator for very cold days
Rear Bedroom showing MVHR cupboard & outlet
Insulation to MVHR intake
Water meter for monitoring installed under kitchen sink
Smart meters installed for 2 year monitoring 
New cupboard built to house meters

Wednesday 16 February 2011

Building Control Viewpoint on Retrofit

Senior Building Surveyor Phil Booth, of Building Advisory Services at Stoke On Trent Council has contributed his comments on the retrofit project at St Lukes St so far. Phil Booth has been inspecting the works as they've progressed, and we grateful that he's offered his comments and views below.

Friday 11 February 2011

Site Manager Ian Davenport's Site Progress Diary

This last few days we have finished the plastering, fitted the kitchen and had the gas and elec meters fitted.
Bathroom now plastered 
Wall-mounted radiators for more space 
Kitchen Installation Begun

Monday 7 February 2011

Site Manager Ian Davenport's Site Progress Diary

The works completed from 2/2/11 to date has been the f/fix joinery and membrane to the extension, plastering to the same and 2nd fix mechanical and electrical to the f/f.
Additional air-tight sealant to cable grommet
Air-tight taping to triple-glazed rooflight 
Patteresses to take WC to insulated wall
Wall-mounted ventilation outlet to bedrooms
MVHR unit in cupboard