Monday 7 March 2011

St Luke St Retrofit Complete!



Great turn out at the open day held at St Luke St for our Retrofit for the Future project for Sanctuary Housing, which shows the level of interest in the realities and challenges of retrofitting our existing housing stock.

Presentations from contractor's Seddon, and Fran and Jennie from ATA gave all present a great insight and overview into all aspects of the project from design to completion on site.

Click here to view ATA's presentation of how we designed to reduce the CO2 emissions at St Luke St by over 80% using Passivhaus Enerphit approach

Thursday 24 February 2011

Site Manager Ian Davenport's Site Progress Diary

During the past week, we have completed the decoration, commissioned the boiler and solar panels, commissioned the MVHR and are completing the external works.

David (Sanctuary's Clerk of Works) and I have just returned from St Lukes and the MVHR is running and the rads are off, the temp in the bedrooms is almost too warm! The ext temp is 13deg and the attached photo shows the solar panels heating to 59deg.

Solar Thermal Info Panel on Rotex Unit
Decorations Complete
MVHR wall mounted outlet to front bedroom
Insulation in Loft & Insulated MVHR intake

Friday 18 February 2011

Site Manager Ian Davenport's Site Progress Diary

Over the last 4 days we've been decorating , testing the MVHR and completing the glazed tiling.
Radiators moved closer to wall for more space

Small 'back-up' radiator for very cold days
Rear Bedroom showing MVHR cupboard & outlet
Insulation to MVHR intake
Water meter for monitoring installed under kitchen sink
Smart meters installed for 2 year monitoring 
New cupboard built to house meters

Wednesday 16 February 2011

Building Control Viewpoint on Retrofit

Senior Building Surveyor Phil Booth, of Building Advisory Services at Stoke On Trent Council has contributed his comments on the retrofit project at St Lukes St so far. Phil Booth has been inspecting the works as they've progressed, and we grateful that he's offered his comments and views below.

Friday 11 February 2011

Site Manager Ian Davenport's Site Progress Diary

This last few days we have finished the plastering, fitted the kitchen and had the gas and elec meters fitted.
Bathroom now plastered 
Wall-mounted radiators for more space 
Kitchen Installation Begun

Monday 7 February 2011

Site Manager Ian Davenport's Site Progress Diary

The works completed from 2/2/11 to date has been the f/fix joinery and membrane to the extension, plastering to the same and 2nd fix mechanical and electrical to the f/f.
Additional air-tight sealant to cable grommet
Air-tight taping to triple-glazed rooflight 
Patteresses to take WC to insulated wall
Wall-mounted ventilation outlet to bedrooms
MVHR unit in cupboard

Monday 31 January 2011

Site Manager Ian Davenport's Site Progress Diary

Today we are finishing the membrane to the extension in preparation for the plasterers tomorrow. As you can see from the photos the elec connection was made today and contact with the smart metering company has been made. We have also started decorating the f/f and will be starting the 2nd fix M&E from the 2/2/11.

Wednesday 26 January 2011

Site Manager Ian Davenport's Site Progress Diary

Since Christmas we have fitted the floor to the rear extension, studded out the extension walls, the slab to the rear step of the extension, patch plastered some and started to fit the last of the windows and doors today.
Triple-Glazed Rooflight Installed 
Membrane taped to floor DPM
Sheepswool wall insulation
Wall membrane taped to floor

Monday 17 January 2011

Architect Post: Thermal Bridge Heat Loss for Dodgy Wall

We are rebuilding the new extension against the neighbours party wall, and insulating with a small amount of insulation.
Site discovered a section of brickwork approx. 1.2 x 1.2m square that sticks out 70mm from the wall, as it looks like a section of the old garden wall was simply built into next doors extension.
Mish-mash of brickwork to neighbouring rear extension party wall
We intend to insulate the party wall slightly in this area with 70mm insulation to minimise heat loss to next door, so this protruding brickwork cuts into our insulation, and we don't have any tolerance in the extension to insulate around, as a narrow site!

The clerk of works for the housing association does not want to cut back this brick, as next doors wall build-up is unknown, so I've done two calculations on this section of wall to consider the effect of forgoing party wall insulation to the square of wall:

Difference in Heat Loss for Party Wall to next door: 
 A x  U1 x ft x Gt
 = 1.08 x 1.769 x 0.25 x 68
=  32.5 kWh/yr
=  0.5 kWh/sqm.yr


Difference in Heat Loss for Party Wall to below ground: 
 A x  U1 x ft x Gt 
 = 0.36 x 1.769 x 0.59 x 68
=  25.6   kWh/yr
=  0.40 kWh/sqm.yr

TOTAL HEAT LOSS = 0.9 kWh/sqm.yr

Would increase heat demand from 23 to 23.9 kWh/sqm.yr

A = Area (m2)
U1 = Difference in U-Value between insulated & non-insulated party wall (W/m2K)
ft =  Temperature correction factor for party wall assuming 15oC low next door & 21oC interior temp & -3oC external temp
Gt = Heating degree hours per year (kKh/a) - used manchester weather data

Internal Wall Surface Temperature of section of wall below neighbours floor level
(Bottom corner):

= Room Temp x (U x Rsi x (Room Temp - Outside Temp)

= 21 x (2.205 x 0.13 x (21 - 10)
= 21 - 3.15
= 17.85 oC (So no mould growth risk)

U = U-Value of non-insulated party wall (W/m2K)
Rsi = Internal Surface Resistance for wall
Outside temp = 10oC as below ground