Since Christmas we have fitted the floor to the rear extension, studded out the extension walls, the slab to the rear step of the extension, patch plastered some and started to fit the last of the windows and doors today.
Triple-Glazed Rooflight Installed 
Membrane taped to floor DPM
Sheepswool wall insulation
Wall membrane taped to floor