Monday 1 November 2010

Site Manager Ian Davenport's Site Progress Diary

Started to support existing chimneys above ceiling level and fit pad stones.
Insert steels to chimneys, this was able to be done by removing the roof tiles and sliding the steel out then back in again. Insert rear steel and joint together.
Chimney breast propped in loft for removal below
Concrete padstone for beam on external wall
(Note: The chimney stacks are being removed as they are a major route for draughts and heat loss, and we will gain additional floor space that has been lost when we internally insulate the external walls).