Thursday, 9 December 2010

Site Manager Ian Davenport's Site Progress Diary

Today we have inserted the foamglas packer to above the steel beam, the windows have been completed and the intello tape fitted to the frames. The temperature has finally got above 3deg and work has started on the rear extension.
Foamglas bearer for steel
MVHR Kit in cupboard
Triple-glazed window installed 
Woodfibre insulation returned at party wall